ICOD APR100 MW performance test
Files processed in your browser

SAMARKAND 1 · TEN-MINUTE METHOD

Performance dashboard

Upload the WMS and inverter count files for each day. Results update as you add days.

Test window21 Sep 2026 – 30 Sep 2026Waiting for daily files

02 · TEST OVERVIEW

Current result

Awaiting data
Provisional APRIncluded days · total energy ÷ corrected POA
Acceptance threshold95% × weighted guaranteed PRG
Included days0 / 1010 still required
Expected test end30 SepExtends for excluded days
Measured energyMWh · included days
Weighted guaranteed PRGMonthly values across test window
Add both source files to calculate the first day. Days are stored in this browser.

03 · DAILY RECORD

Test days

0 files loaded
DateCalculation statusPOA kWh/m²Energy MWhAPRPRG95% PRGDecisionReason

04 · TEST TREND

Daily APR vs guarantees

Daily APR95% PRGGuaranteed PRG

05 · SELECTED DAY

Day detail

Upload a day to see its ten-minute measurements and operating conditions.
Calculation basis

For each ten-minute interval, Eact = selected average power (MW) × 1000 ÷ 6. POA is the average of the ten pyranometers, then converted to kWh/m² using ÷ 6 ÷ 1000. Module temperature is the average of fifteen sensors. APR = ΣEact ÷ [120,863 kWp × Σ(POA × (1 − β × (Tmod − Tmeas)))], with β = −0.003. Daily POA must be at least 3.5 kWh/m². Inverter counts affect day inclusion only when POA exceeds 100 W/m²; 92 units is 100% availability. Grid availability is entered manually.